Update: 6/25/2014
- Preparing 8 units for field trial with USX
End of April 2014Field Trial: Schedule truck for mid may (After the week of May 12th)- Send fuel sensor specs to Ken on 04/30/2014 for review by Mike Auvil
- Coordinating with USX to get a USX truck for install on 9, 10, 11 July 2014
Goals
Background and strategic fit
Assumptions
Requirements
# | Title | User Story | Importance | Notes |
---|---|---|---|---|
1 | ||||
User interaction and design
Questions
Below is a list of questions to be addressed as a result of this requirements document:
Audience | Question | Outcome |
---|---|---|